Application Number: Mod2021/0444


Description:
Section 4.56 Court Consent - Modification of Development Consent N0123/17 for Demolition of an existing aged care facility and construction of a new residential aged care facility
Application Type:
Section 455 Modifications
Status:
Approved
Submitted:
01/07/2021
Exhibition Period:
23/07/2021 to 13/08/2021
Determined:
20/10/2021
Determination Level:
Sydney North Planning Panel
Cost of Work:
$ 34,163,225
Officer:
Jordan Davies
Submissions:

Related Applications:
Map

Other Applications
Principal Certifier OC2022/0262
Demolition of an existing residential care facility and construction of a new 156-bed residential aged care facility - Occupation Certificate covering Stage 2 (the final stage) of the new 147 bed aged - S180203-OC-2 (Submitted: 03/05/2022)
Construction Certificate CC2021/1526
Construction of new 147 bed aged care facility over two stages- Modification to S180203-CC-3 and S181203-CC-3A to include domestic style resident kitchens with supporting ‘back of house’ sculleries, in lieu of the currently documented serveries. Modifications to the Dirty Utility & Lifter Store on Ground Floor and Level 1 to include a Cleaners’ Store. Modification S180203-CC-3C to include relocation of two pergolas and amendment to associated pathways and doorways - S180203-CC-3C (Submitted: 14/12/2021)
Section 455 Modifications Mod2021/0444
Modification of Development Consent N0123/17 for Demolition of an existing aged care facility and construction of a new residential aged care facility (Submitted: 01/07/2021)
Principal Certifier NOC2022/0027
Demolition of an existing residential care facility and construction of a new 156-bed residential aged care facility (Submitted: 17/06/2021)
Principal Certifier NOC2020/1519
CC4: Construction of new 147 bed aged care facility over two stages - Modification to S180203-CC-3 to include corridor handrail and corridor end circulation area variation performance solutions - S180203-CC-3A (Submitted: 10/12/2020)
Principal Certifying Authority IOC2020/0175
Interim occupation certificate for Stage 1 of the new 147 bed aged care building - S180203-OC-1 (Submitted: 26/11/2020)
Construction Certificate CC2020/1178
CC4: Construction of new 147 bed aged care facility over two stages - Modification to S180203-CC-3 to include corridor handrail and corridor end circulation area variation performance solutions - S180203-CC-3A (Submitted: 29/10/2020)
Principal Certifier NOC2020/1291
Construction of a new 147 bed aged care facility over two stages - S180203-CC-3A (Submitted: 26/10/2020)
Construction Certificate CC2020/0221
Construction of a new 147 bed aged care facility over two stages - S180203-CC-3 (Submitted: 11/03/2020)
Principal Certifier NOC2020/0279
Construction of a new 147 bed aged care facility over two stages - S180203-CC-3 (Submitted: 11/03/2020)
Section 455 Modifications Mod2020/0007
Modification of Development Consent N0123/17 for a new residential aged care facility to amend condition 22 to require compliance with an Environmental Management Plan. (Submitted: 10/01/2020)
Construction Certificate CC2019/0846
Earlywork Construction Certificate including, Piling Remedial works Construction of OSD in ground services, footings, ground gloor slab, first floor slab and frames and trusses including structural steel to front entry - S180203-2 (Submitted: 15/08/2019)
Principal Certifier NOC2019/0907
Demolition of an existing residential care facility and construction of a new 156-bed residential aged care facility - S180203-2 (Submitted: 02/08/2019)
Section 455 Modifications Mod2019/0342
Demolition of an existing residential care facility and construction of a new 148 bed residential aged care facility (Submitted: 17/07/2019)
Construction Certificate CC2019/0362
Demolition of an existing residential care facility and construction of a new 156-bed residential aged care facility - S180203-1 (Submitted: 09/04/2019)
Development Application N0123/17
Demolition of an existing residential care facility and construction of a new 156-bed residential aged care facility (Submitted: 07/04/2017)